Completion of construction of a new high-bay warehouse. Purchase of: a new robotized paint line, 2 modern turbine mixers .
Completion of construction of a new high-bay warehouse. Purchase of: a new robotized paint line, 2 modern turbine mixers .
Purchase: 2 automatic core machines, 5-axis milling machine. Reconstruction of the access road to the foundry. Commissioning of the casting cooling plant.
Project Implementation: Closed-loop Economy. Purchase of a horizontal 2-pallet milling center from Okuma.
Further development of the machining department. Purchase of more than a dozen CNC machine tools.
In the first quarter of 2017 we plan to launch a new Disamatic D3 Z555 automatic line and the new melting plant department with two induction furnaces of 2×6 tons.
Rebuilding the entire foundry. Construction of new production halls and a state-of-the-art bulk processing station with a capacity of 120 tons/hour.
Commissioning of a new molding line with a DISAMATIC 130A automatic machine and a foundry dust removal station.
Launching a new department of mechanical machining with pattern shop.
Purchase of 2 Koyama machines for precision grinding and a 5 axis milling centre.
Starting construction of a new melting plant department with a capacity of 5 tons/ h.